3

PIR date at start of month

 4 weeks ago
source link: https://community.sap.com/t5/enterprise-resource-planning-q-a/pir-date-at-start-of-month/qaq-p/13678901
Go to the source link to view the article. You can view the picture content, updated content and better typesetting reading experience. If the link is broken, please click the button below to view the snapshot at that time.

PIR date at start of month

Hi Planning Experts 

When creating PIR in demand management requirements are assign to 1st day of the Month. But business want to assign last day of the month. 

Based on few post in the community i tried OMI4, it is not working as the customer requirement fulfillment is also assign to last day of the month. 

https://community.sap.com/t5/enterprise-resource-planning-q-a/pir-date-at-start-of-month-week/qaq-p/...

Regards, 

Varma 


About Joyk


Aggregate valuable and interesting links.
Joyk means Joy of geeK