Hi Planning Experts
When creating PIR in demand management requirements are assign to 1st day of the Month. But business want to assign last day of the month.
Based on few post in the community i tried OMI4, it is not working as the customer requirement fulfillment is also assign to last day of the month.
Regards,
Varma